Projects:
Heyington Avenue Bridge
Melbourne, Victoria
Off Site Installation:
Permadec panel delivery was co ordinated with the site team to ensure that the panels arrived to site once the steel girders had been delivered.
With the steel girders now at ground level, the Permadec panels were then installed by the project team.
Offsite installation ensure that an efficient install of Permadec panels was achieved whilst also reducing costs through reduced cranage and by enhancing program with an efficient install. Risk of working at a height was also greatly reduced.\
Products Supplied:
- Permadec Type 3 standard panels.
- 150mm rib centres to suit reinfocement details and prevent on site clashes.
- Overall panel height of 59mm
Key Facts
- Offsite installation of Permadec panels reduced working at height requirements.
- Single lift installation of the 90m, 232 tonne arch structure, streamlining the overall construction sequence.
- Minimised possession, crane time and risk on site.
Project: Heyington Avenue Bridge as part of the North East Link Project - Burke to Tram Roads
Client: Major Road Projects Victoria
Main Contractor: Laing O'Rourke & Symal
Engineering Consultancy: WSP & Arcadis
Stage: Delivered